As we approach the qualification date for Phase 4 of the UK’s Energy Savings Opportunity Scheme (ESOS), let’s recap what your requirements are if you’re required to comply.
The Energy Savings Opportunity Scheme Regulations 2014 introduced a 4-yearly cycle of mandatory energy assessments and energy saving opportunity identification for large undertakings* (or corporate groups containing large undertakings) in the UK.
*Your company is classed as a large undertaking under ESOS if you have either:
- 250 or more employees in the UK; OR
- Fewer than 250 employees, but an annual turnover of £44million+, AND a balance sheet exceeding £38million.
(If a corporate group contains at least one UK subsidiary that must meet ESOS requirements then the entire UK group must participate even if a smaller subsidiary would not qualify on their own.)
Phase 3
The final requirement of Phase 3 is the second annual action plan progress report, due 5th December 2026. Actions plans must be submitted through MESOS and must be signed off by a company director. This second annual progress update report must include the energy saving measures implemented since the first annual progress update report, whether measures originally planned in the action plan have been completed, and an estimate of the energy savings that have been achieved as a result of the measures described.
Phase 4
Companies that meet the large undertaking threshold above on 31st December 2026 will be captured by Phase 4 of ESOS and will be required to comply with its requirements.
The first requirement will be the following year on 5th December 2027 which is the compliance notification deadline by which participants must have notified their regulatory body* and completed their ESOS assessments.
*The regulatory bodies for the different UK jurisdictions are as follows:
- England: Environment Agency
- Wales: Natural Resources Wales
- Scotland: Scottish Environment Protection Agency
- Northern Ireland: Northern Ireland Environment Agency
By 5th December 2028, participants in Phase 4 must submit their energy efficiency improvement action plan, and for the subsequent 3 years must report annually on progress against the action plan. The final requirement for Phase 4 participants will therefore be the submission of their third annual action plan progress report, due 5th December 2031.